Case Study

Harbury Cutting

Project

Harbury Cutting

Client

Network Rail

Location

Harbury, Warwickshire

Sector

Rail

Principal  Contractor

Murphy

Scope of Work

Harbury Cutting Slope Stabilisation (Emergency Response)

Specialist Contractor

Vertical Access Ltd

Geotechnical Designer

RJM

Consultant Engineer

Tony Gee & Partners

Materials Supplier

Soil Nails from Minova

The Scope

Harbury Cutting was constructed in the 1840s by Brunel and at 34m deep is recognised as the largest hand dug rail cutting in the world. The cutting had a history of geotechnical failures, which led to a major disaster where the embankment crest dropped by 4m and over 300,000 tonnes of material slid towards the track. The landslide took away part of the west portal which is a curved mass brickwork structure over 50m wide and 15m high.

The Challenge

During ongoing works on a minor slip, Vertical Access Ltd was requested to install a 290-meter catch fence which successfully limited the movement of a landslide, preventing it from affecting the active railway track. When the major landslip occurred, an emergency plan was instigated to stabilise the cutting and portal. We were brought in to perform soil nailing on the slope adjacent to the portal and to install anchors through the portal to prevent further collapse.

 The Vertical Approach: Safety, Quality, Innovation & Agility

Safety

Safety was a critical concern due to the continuously moving slope, which required constant monitoring to protect the operatives working on the slopes and structures. The presence of water jets during trial drilling highlighted the complex and hazardous conditions, necessitating rigorous safety protocols and continuous alert systems to ensure the well-being of all personnel on site.

Quality

Quality control was paramount in addressing the unstable ground conditions. The evolving design, influenced by real-time feedback from trial works, included the use of sulphate-resisting grout to enhance durability. The precision required for diamond coring through 2-metre-thick brickwork and the installation of soil nails and support-plates demanded meticulous attention to detail, ensuring the stabilisation efforts met the highest standards.

Innovation

Innovation was key to overcoming the project's challenges. The discovery of a vertical fault line of limestone necessitated adaptive strategies. Vertical Access utilised large excavators up to 67 tons, fitted with TEI drill rigs and masts, to handle the 20-meter long soil nails. The design of a custom platform supported by Mabey System 160 brackets and rope access systems for brick re-casing demonstrated ingenuity in providing a safe and effective solution for the complex stabilisation tasks.

Agility

The project required exceptional agility in mobilising resources, plant, and materials under tight deadlines. Network Rail's commitment to reopening the railway within nine weeks demanded 24/7 operations. VA coordinated a diverse team drawn from sites across the UK, working in a rolling program to drill and mesh, ensuring timely completion. The ability to adapt to evolving ground conditions and collaborate effectively with Murphy for the safe and efficient operation of excavators, dumpers, drilling plant, and rope access personnel was crucial to meeting the project’s stringent timeline.

Gallery

No items found.

Outcome & Feedback:

VA’s comprehensive approach to safety, quality, innovation, and agility ensured the successful stabilisation of the landslip area. The installation of soil nails, the support of the brick portal, and the completion of all tasks within the tight schedule allowed the railway to reopen on March 13th, 2015, ahead of the planned deadline. The project exemplifies effective emergency response and engineering excellence in challenging conditions and was even commended by Mark Carne (Chief Executive of Network Rail)

TESTIMONIAL

“Thousands of passengers, and thousands of tonnes of freight, rely on this vital route every day. We have been working around the clock and are able to reopen the railway three weeks ahead of the original estimate. 
Mark Carne
Chief Exective, Network Rail

Get in touch

Book a discovery call to discuss what we can bring to your business
Rope Access Technician performing an inspection above Manchester Skyline
Contact us today to discuss how we can help your project!
Unit E211,Warmco Industry Park,
Manchester Rd, Mosley,
Ashton-under-Lyne  OL5 9AY